Together we rebuilt more than just a wall.
Reconstruir a Região Centro Juntos!
  • Social
  • Arroteia, Souto da Carpahosa, Leiria

Together we rebuilt more than just a wall.

Help us rebuild the retaining wall on one side of the churchyard of the Arroteia Chapel in the parish of Souto da Carpalhosa, to ensure the safety, preservation and dignity of t...

Help us rebuild the retaining wall on one side of the churchyard of the Arroteia Chapel in the parish of Souto da Carpalhosa, to ensure the safety, preservation and dignity of this space of faith dedicated to Nossa Senhora dos Remédios.

The small village of Arroteia, located in the parish of Souto da Carpalhosa, municipality of Leiria, has a chapel dedicated to Nossa Senhora dos Remédios. This chapel is much more than a religious space; it is a meeting point, a place of faith and tradition for the entire local community.

For generations, this place has hosted celebrations, weddings, funerals, vows, and significant moments in the lives of many families, and is a living symbol of our collective identity. It is believed that the first hermitage built on the site where the chapel now stands dates back to the 14th century. During the French invasions, the chapel was partially destroyed, but it has been restored over the years thanks to the work and support of the local population, as well as the costs of its continued preservation.

Recently, one of the churchyard's retaining walls, measuring 41m in length and 2m in height, collapsed due to the various severe weather events that occurred this winter. The current situation represents a risk to all who frequent the space, especially during celebrations and events, and also a risk to the preservation of the foundations of one of the chapel's walls.

For these reasons, the reconstruction of this wall is urgent. It is not just a construction project, but also the protection of a space that belongs to the entire community, ensuring safety, preserving heritage, and keeping alive a tradition that spans generations.

The chapel committee was recently elected and does not have sufficient funds for the immediate reconstruction of the wall. The small local population also suffered significant damage to their homes and yards due to Storm Kristin, and therefore currently lacks the financial capacity to contribute to the wall's reconstruction. Thus, with your contribution, it will be possible to rebuild  the wall and all  churchyard structure more quickly and ensure the safety of worshippers and passersby on the adjacent road.

Every bit of help counts. Every contribution will go towards laying a stone in the new wall.

About the author

The promoter is the Arroteia Chapel Committe, belonging to the Parish Church Factory of Souto da Carpalhosa.

This committee is composed of only four volunteers plus the parish priest of Souto da Carpalhosa, who is also the president of this committee, and who recently appointed it on April 7, 2026.

Given the urgency in rebuilding the wall and funds to carry out the project, the Chapel committee is promoting this campaign in order to gather all possible contributions.

Budget and due dates

The wall to be rebuilt will be 41m long and 2m high. It will be constructed of smooth stone blocks approximately 1m long x 0.90m wide and 0.70m high, set on a reinforced concrete foundation.

The following costs and work are anticipated for the construction of the wall:

- Removal of debris from the old wall to a landfill and earthmoving - €1,500

- Construction of a reinforced concrete foundation for laying the stone blocks (length: 41m, width: 0.90m, and depth: 0.60m) - €4500

- Construction of the new wall using smooth stone blocks (see attached budget) - €11,430

Other unforeseen costs - €750

Total cost excluding VAT: €18,180

Total cost including VAT : €22,361.40

Project schedule :

- Removal of debris from the old wall to a landfill and earthmoving to clear the road and construct the wall : Planned for the week starting on April 20 2026, and is expected to be concluded in 1 day.

- Foundation construction and wall raising : This will begin as soon as the committee has secured funding for the complete execution of the wall and the construction company is available. Completion of the work should take between 3 and 4 weeks after commencement.

 

 

 

Fri, 24/04/2026 - 20:39

Campaign launched

21/04/2026

0 members of the PPL community
support this campaign

  • 0
    new backers

  • 0
    recurrent backers

  • 0
    anonymous backers

Meet the people helping this dream come true